 A general overview of the DMU engine
shop. Storage racks separate the rectification and
rebuild sections
|
Early Engine Overhauls
With all the DMUs being or due
to be introduced throughout the country, the LMR
allocated an area in Derby works to deal with the repair
and overhaul of the engines. Good forward planning saw a
workshop in which tender tanks had been repaired emptied
and completely reconditioned early in 1955. By the
allocation of a separate shop, the area was properly
arranged in sections with complete separation of
dismantling and assembly, personnel and components. This
allowed the work to be done more efficiently than if they
were handled in the already established diesel erecting
shop. The shop was reconditioned and started work at the
end of 1955.
Batches of dismantled components found
fit for further use were sent to a central store, and not
direct back to the same engine from which they were
taken.
At the entrance end of the shop was a
30ft x 47ft annexe in which the engines were cleaned
externally, stripped, and then all components cleaned.
Thor Pneumatic hoist blocks of 2,000 lb. capacity,
mounted on overhead runways, were used for handling, and
transport from the stripping and cleaning annexe was by
roller conveyer.
Approximately one-third of the main
shop, which was 186 ft. long by 47 ft. wide, was used for
component inspection, rectification, and the storage of
components and sub-assemblies. Following the
small-component store was a rebuild section and storage
compound for the larger components such as cylinder block
and crankshaft assemblies. The assembly line for the
rebuild of complete engines extended from this point to
the despatch bay. On one side of the despatch bay was a
dynamometer test bed and on the other side offices for
the foreman, storekeeper, and clerical staff. The fuel
injection equipment room was in an extension of the main
shop, adjacent to the office block. All work benches were
fitted with aluminium tops and the shop floor was tiled.
Heating was by blower fan steam radiators and the general
shop lighting was supplemented by extensive lighting over
the benches.
Stripping and Cleaning
When an engine was received in the
stripping annexe, equipment such as the fuel pump and
starter motor were removed, and the engine was then
passed through a twin-chamber high-pressure detergent
spray washing plant for external cleaning. The large
chamber of the spray booth was 63in. by 75in. by 10ft.
long and was capable of taking any completed diesel
engine of vertical or horizontal type up to 950hp. Two
Girdlestone pumps each delivering 300 gal. per min. at
60ft. head supplied the multi-spray cleaning nozzles.
Another pump was provided for emptying the slump. The
spray booth had a 1,000-gal. capacity sump and the steam
heating of the solution by steam coil was
thermostatically controlled. This initial cleaning was
followed by dismantling of the engine into its
sub-assemblies. These were loaded into trays and passed
on the roller conveyor through the smaller chamber of the
spray booth which measured 51in. by 51in. by 10ft. long.
Sub-assemblies were then completely dismantled at benches
alongside the conveyor, the components loaded into
baskets, and thoroughly washed and cleaned and carbon
removed in a steam heated bosh. Three boshes were
installed, two measuring 66in. by 72in. and one 42in. by
72in. These were fitted with a Keith Blackman 6in. blower
and 36in. fume extraction fans. In the transfer from the
stripping section to the main shop, the clean components
were divided into eight streams, comprising cylinder
blocks, pistons and connecting rods, auxiliaries, oil
pumps, crankshafts, cylinder heads, crankcases, water
pumps, manifolds and covers. All loose studs, bolts, and
nuts were dropped into a container, and after sorting
into respective sizes returned to stores. The recovery
percentage was high and the job was carried out by
disabled personnel.
Replacement of Defective Parts
In the main shop inspection of the
parts, covering visual, dimensional, and hydraulic
pressure testing as required, was the first operation.
Paint colour coding was used on each part by inspection
to identify parts which may be refitted, rectified, or
scrapped. Useable parts passed immediately to the
sub-assembly stores, and replacements for scrapped parts
were drawn on the inspector's authority from the works
main component store. This system ensured that for each
engine received a complete set of parts was available in
the sub-assembly stores when required for the rebuild.
With the exception of certain partly-worn items, such as
cylinder blocks, pistons and connecting rods, which by
matching could be used for a further period, no attempt
is made to rebuild the engine from the same
sub-assemblies originally used.
The inspection bay was well equipped
with the special tools, gauges, and a water test fixture
required for each engine type. All crankshafts were
examined on a Fel-Electric magnetic crack detector, and a
Hanovia ultra-violet-ray lamp was used for crack
detection on smaller components. Valve springs were
loaded and measured on a Britool dial-reading spring
tester. Racks and bins at the end of each inspection
bench were used for the storage of parts requiring
rectification. If welding, machining, or crank regrinding
was required the parts were sent into the main works.
Equipment was installed in this works in 1959 to
investigate the extent to which electrochemical means
could be used in the building up of worn parts. This
equipment used the Dalic process of metal depositing.
Fuel-Injection Equipment
The fuel pump, removed from the engine
immediately after receipt at the works, was sent, along
with the injectors, to the fuel-pump repair shop. Here
was a "clean" room, 35ft by 27ft, with fitted
benches and cupboards on each side and the calibrating
machines and storage racks in the centre. The floor,
benches and racks were linoleum covered. To secure
maximum cleanliness all pumps and injectors were
dismantled and cleaned before being brought into the
"clean" room. Each set of cleaned parts was
delivered in a tray provided with a socket for each
component. Pump plungers and cylinders were first tested
for rate of leakage on a Merlin comparator, and injector
valve seats were ground and lapped on a Merlin
Servicemaster. Each bench assembly station was fitted
with an air-pressure cleaning nozzle discharging into a
fixed tundish. The tundish was connected by trunking to
an extractor fan, thus ensuring immediate removal of dust
and foreign matter. Plastic hoods were used to cover all
equipment until required for immediate use, and on the
benches were roller-mounted canvas covers for the
overnight protection of work in progress. For pump
calibration there was a Merlin Calimaster and a Hartridge
test machine; and on the injector bench were three C.A.V.
hand-pump test units.
Rebuild and Testing
For the rebuilding of complete engines
the crankcase-cylinder block forming the main carcase was
mounted on a portable stand, and ten of these stands
formed the assembly line. The portable stands provided
for flexibility in the progress of an engine along the
line, according to rebuilding priority. Movement of
engines was by a battery electric pallet transporter.
From the accumulated stock of components in the repaired
detail storage the sub-assemblies were made up and then
transferred to the assembly storage racks situated at the
end of each line in readiness for final assembly. A
continuous bench at the side of the track was used to
keep equipment off the floor during assembly. For the
final assembly a series of portable erecting stands were
arranged across the ends of the eight belt lines.
Erection was performed in four stages. Each stand and
unit were moved to the end of each pair of belt lines for
the respective sub-assemblies to be erected. Patrol
inspectors on the line ensured that the required high
standard of cleanliness and workmanship were maintained,
and that the complete build is to specification
requirements.
At the completion of the rebuild the
engine, fitted with auxiliaries, was run-in and load
tested on a Heenan & Froude type DPY5 hydraulic
dynamometer. This was suitable for testing engines up to
640hp. Driving through the brake was a 35 h.p. 300-800rpm
variable-speed electric motor. This was used to motor the
engine for a short period to remove initial stiffness and
circulate the oil. Following a run of 30 min. at no load
the engine was run for 2 ½ hr. with progressive load
increments at speeds between 1,000 and 1,800 r.p.m. This
was followed by a series of tests over the same speed
range at the maximum rated output for each speed. Fuel
consumption was checked with a Flowrater meter, measuring
the rate of fuel flow in c.c. per sec. The test bed was
equipped with a 400-gal. fuel tank, and a 100-gal.
cooling-water header tank fitted with a Drayton automatic
temperature regulator. Lifting the engine on and off the
test bed and on to the transporter vehicle after painting
was by a 1 ton capacity overhead travelling crane. This
single test bed was soon inadequate to deal with the flow
of engines then being handled by Derby, and by 1959
additional test beds were being installed in an adjacent
building.
In addition to the overhaul and rebuild
of complete engines, an increasing amount of component
repair work was carried out for other diesel depots in
the London Midland Region. A stock of reconditioned
components was held in store ready for immediate issue as
replacements when defective parts are received. The
defective parts were then reconditioned and returned to
store, or if not repairable new parts are issued as
stores replacements.
|