Next Saturday, May
31st, we are going to remove my spare engines and
gearboxes from Chinnor. Gordon Titmuss has arranged the
HGV. All I need to do is pay for the diesel. Sunday will
see a start on the guttering.
Saturday May 31st
arrived and I was at Chinnor by 0900 hrs. ready to get
the engines and gearboxes prepared for transportation. By
1130 hrs. the wagon duly arrived. It was a bit of a slog
getting the machinery onto the wagon as it had side
curtains and the crane jib would not fit under the top.
By 1330 however by good old brute force and ignorance we
had the wagon loaded and were away from the depot by 1400
hrs.
Arrival at Chinnor was
by about 1530 hrs. and as soon as Dave was available the
three engines and two gearboxes were craned off. Once
again we had trouble with the crane jib fitting under the
side sheets. By 1600 hrs. they were stored and covered on
the ground ready for eventual storage in one of the flat
wagons. The tarpaulin donated by Harry Balchin covered
all three engines and two gearboxes with plenty to spare.
Sunday was the day I
had designated to start removal of the guttering. I
decided which pieces were to be removed and duly set up
the scaffolding to be able to reach the roof. 5 pieces
were to be removed which would allow access to the body
panels that needed attention.
The coach bolts were
removed by grinding off the nuts and knocking through. A
couple were unbolted to ensure I could get replacement
bolts. The guttering was screw fitted over the doors but
90% of the screws either sheared off or refused to move
and had to be ground off.
By the evening all 5
pieces were off the on No. 1 side. I made a start on
removing the rusted panel next to the guard's van door.
As it was well welded in place I left the final removal
until the next weekend.
I managed to get
replacement coach bolts easily from Bletchley Timber
which surprised me. 136 in all!!. During the week I
cleaned up the guttering at home ready for replacement
the next weekend. I also took delivery of the Mason's
green paint needed for the repainting on Friday June
6th..
The roof panels and
the side panels are not joined together instead there is
a 1/2" gap. This is because the roof is galvanised
and the side panels sheet steel. The roof panels are
welded onto curved roof formers and these are in turn
welded onto the side frame formers. The side sheets are
in turn welded onto the side formers. It is the guttering
pieces that form the seal between roof and side panel and
therefore needs to be properly sealed.
The removal of the
rusted piece proved to be time consuming job not being
completed until late Friday afternoon. Most of the
interior metalwork had rusted through and the grey
internal window frame had to be removed. This will need
to be rebuilt. The wooden to metal window frame fitting
had rotted and was removed for renewal as per the main
saloons. The cutting of the replacement piece was
relatively straightforward even if I did cut it a bit
short! This was held in place by screw fittings and ready
for welding by Dick for Saturday June 7th.
Dick tried my MIG
welder but it is evidently not up to the job. We refitted
the piece reusing the screws so that the guttering could
be refitted and left the welding until Dick could bring
his gas welder. The other smaller pieces I managed to
weld into place quite successfully and with a touch of
filler finished the job.
The roof panels and
top of the side panels were patched and/or cleaned down
and primed and painted. The gap was filled with best
silicon lead and plastic pipe sealant. The guttering
itself was coated with a liberal coating of sealant and
refitted. The bolts were reasonably easy to refit and by
the end of the weekend three of the five were back in
place. The screw fittings above the door however were not
so easy to refit and I had to redrill the guttering to
take new screws. The old holes will be filled and rubbed
down to size.
The final two pieces
will be refitted over the weekend of June 14th &
15th. Once completed the No. 1 side is ready for
preparation for repainting.
Kevin has given me
some plywood sheets that may be suitable for the inner
door inserts. I shall make one up to the measurements of
the old sheet steel inserts and see how they look in teak
stain and varnish.
On Thursday June 12th
I was passed out for shunter/guard by the Guard's
Inspector from the Great Central but I'm not going on the
roster until the unit is ready. The inner door panel was
tried and found to be approximately 1/4" too wide. I
shall trim it down ready for the weekend.
Saturday June 14th was
a day that started fine but dull and got worse. However I
managed to get the final bits of welding completed, the
roof/side panels cleaned down and the remaining two
pieces of guttering back in place and sealed up. When it
started to rain there were only two small leaks
immediately noticeable and neither were behind the
guttering but through two of the holes left after
redrilling. These can be tackled during the next dry
spell. The door insert fits well and with a small
adjustment the remainder can be made to the same size and
pattern.
I tidied up the saloon
and left at about 1600 hrs.
Sunday dawned grey and
rainy so I decided to have a day off. In fact I managed
to reconstruct the guard's van window and finish off the
first of the door inserts for trying later in the week.
During the following
week I managed to get a half day in on site on Tuesday
June 17th. The last major piece was cut out of the body
panel and a new piece fabricated and welded in place. The
guttering was inspected and the two leaks tracked down.
All bolts were tightened up using a spanner. Upon testing
the guttering appeared to function correctly. The insides
of both saloons were then swept out and tidied up.
This leaves the
guard's van welding to be completed then the No. 1 side
is ready for cleaning down and filling where required
ready for painting.
I have asked for the
unit to be separated from the Mk. 1 coach and the Class
45 so that I can work on removing the brake vacuum
cylinders. Similarly it will facilitate the use of the
scaffolding when working on the repainting of the front
of the cabs.
The following weekend
was one of rain and winds so any work on the outside was
abandoned apart from getting the scaffolding in place for
Dick.
I ran up the engines
for an hour first thing in the morning. Both engines
started with no problems. Saturday was spent in removing
the No. 2 side internal door panels and renovating the
window mechanisms. All windows and mechanisms in the main
saloons are now in full working order. Even the 'unglued'
ones on the No. 1 side work reasonably well.
The rest of the day
was spent in cleaning down the glass starting with the
eight small glasses and ending with one of the large
panes.
On Sunday June 22nd
the unit was shunted. After discussions with Nick and
Dick I am now ready to begin the removal of the two
vacuum cylinders. Dick finished off the welding on the
guard's van and now the No. 1 side is complete except for
the rewelding of the bottom corner(s) of the side panels.
These can be done from the ground when the scaffolding is
across the rails on the front of the unit. The top half
of the No. 1 side can now be rubbed down etc. ready for
filling and painting. The guttering is holding up fine to
the weather. I may spend a few days and top coat the roof
as it is but we will see how the vacuum cylinders come
out first.
The removal of the
vacuum cylinders will require removal of one set of brake
gear from one end of each bogie. On the No. 1 bogie the
main brake actuating arm will need to be removed but not
on the No. 2 bogie. The No. 2 bogie has enough room to
ease the cylinder forward and down but the No. 1 bogie
does not. The main problem will be the tightness, and
size 11/16 Whitworth (30mm), of the bolts and the lack of
room underneath the bogie. I believe that if the cylinder
is dropped between the sleepers then by pinch barring the
unit from over the cylinder we can manually lift it out
and then crane it into Dick's wagon.
The following week was
the wettest week in June for many a year and by Friday
the unit was stood in a sea of muddy water. Friday
morning was spent in digging out the remains of the brick
arch very conveniently left in the four foot in front of
the unit. The sleepers it was left on were then moved
into a position outside the rail on the number two side
to provide better footing on that side. Drainage channels
were dug along the No. 2 side to alleviate the flooding
of the sleepers and by 1100 hrs. the waters were receding
enough to start work.
two metal sheets
approximately 4 ft. square were placed under each bogie
and a pallet dry enough to sit on was placed under the
buffer beam at each end. The No. 1 end was tackled first
as it had the most to dismantle. The main arm from the
cylinder rod to the brake gear has a bracket to stop
excessive movement in case of any pin failure. This is
held on by four bolts and was the first piece to be
removed. This allowed the arm to rotate clear of the
cylinder and brake gear.
The brake adjusting
bars were next to be released by knocking out the pin at
the rear of the wheel and unscrewing the adjuster at the
front. One side came off easily the other needed a bit of
persuasion.
The brake hangers and
bar were next to come down. The hangers and bar are held
in position by two pins situated above the bogie. The
hangers then pass through a channel which allows fore and
aft movement as the brakes are applied and released. The
hangers have oil lubricated rubbing plates to minimise
wear in this fore and aft movement. The bar that holds
the two hangers in place have two fixings on each hanger.
The upper holds the brake block assembly and the lower
the bottom end of the hanger.
The bar was packed up
and the pins removed. The packing was then removed and
the assembly allowed to fall to the ground. The pins were
then replaced in the hanger brackets. I think the whole
assembly will need to be dismantled and the bushes looked
before replacing. If it is a one man job it definitely
will need to be in its constituent parts before
rebuilding.
The main bar which
takes the up and down motion of the cylinder and converts
it into fore and aft movement of the brake rigging is
held in place by two 'V' shaped brackets. These brackets
are held by 4 bolts each and are not easily removed with
the bogie still under the unit. However after much
heaving and straining it too fell to the ground.
The final task was to
remove the vacuum release valve and associated pipework.
This was an easy task with all nuts, bolts and jubilee
clips coming undone relatively easily after an
application of WD40.
On Saturday the No. 2
end was started. The same task had to be performed at
this end with the exception of removing the main bar. I
began at 0830 hrs and by 1030 hrs was soaked to the skin.
I had managed to remove the brake assembly only. I
decided that that was enough for the day and was about to
go home and get dried. At this point Dave Stokes decided
to dig a drainage channel to alleviate the flood in the
main part of the yard where Colwyn's frames were stood.
This was for two reasons. One, the frames were due to be
removed for restoration and two the two SR box vans were
due to be moved there on a length of track shortly after.
I decided to help. We
dug out a channel across the road and along the No. 1
siding and this seemed to clear the water albeit slowly.
Dave then found a length of steel pipe that could be laid
across the road and be left permanently in situ. This we
did and the waters slowly subsided. By this time the
weather had taken a turn for the better so I had lunch
and stayed.
Eventually I managed
to remove the stop bracket and all the piping etc. except
for the cylinder rod cover. This I left until Sunday.
After an afternoon of
shunting and signalling I left about 1730 hrs in the
middle of a torrential rain storm.
Sunday came and was
misty but not raining. I finished off the No. 2 cylinder
and prepared for Dick to arrive to assist in removing the
cylinders. As I couldn't remove the rods from the
cylinders I made a wooden piece to stand on top of the
trolley jack to accommodate the bottom of the rod and
support the bottom of the cylinder whilst we removed the
bolts.
Kevin, Nick and Dick
arrived at about 1100 hrs and despite Dick's hangover
both the cylinders were out by 1300 hrs.. Two people
working together certainly make it a lot easier. Nick and
Dick rolled one down the yard ready for craning over and
Kevin and I rolled the other one to the same place. The
two cylinders on the back of Dick's pick-up by using the
yard crane.
They were dropped off
at the SVR on the Tuesday afternoon.
The rest of the Sunday
afternoon was spent in looking at the Class 117s brake
gear and noticing it was exactly the same as 55003's.
This weekend has seen another big step completed and
hopefully with the cylinders back in late July or early
August the unit will be a rolling chassis by the end of
August.
Following on the
removal of the vacuum cylinders attention was then
refocused on the body work. Starting on Saturday July 5th
at the secondman's side of No. 2 cab the refurbishment
was begun. The rusted spots were ground out and the
surface was then 'roughed up' by using a rotary drill and
discs. This was a mistake as all the uneven marks on the
surface were there for all to see once the red oxide was
applied.
As I worked along the
side and by the guard's door I found the best way was to
use wet and dry paper and just rub down the surface. The
ground out sections need filling and rubbing down to the
correct contour.
By Sunday evening I
had reached the first compartment door and left it there.
The following week I
was on holiday. I spent the Monday at home with a cold
but continued with the rubbing down on Tuesday morning. I
had purchased some coarser wet and dry of 180 grade. This
made all the difference. The surface came down nicely and
I was going to use it for the rest until I spoke to Dick
the following Saturday.
Dick and Gary had used
a DA sander on the Peak and this produced a good surface
to paint on. So after speaking to Dave Young, who will
bring in the sander next weekend, I can continue then.
The brake gear was
further dismantled so that one person can now replace the
parts once the cylinders are back in situ. Similarly all
the component parts were wire brushed and repainted in
chassis black. New split pins have been purchased to
replace those removed.
The main job on Sunday
July 13th was to clean down and apply polish to the
flooring in the saloons. Dick's father provide an
suitable 5 litre bottle of liquid polish and both saloon
floors were treated appropriately.
I arrived late on the
railway on Saturday 20th July but Dave was there and had
brought the DA sander. As I was so late all I had time to
do was clean down and repaint the remainder of the
dismantled brake rigging.
Sunday however was
spent in sanding down the work I already had done on the
body sides. By 1600 hrs. I had managed to sand down from
the cab corner to the guard's van door. It was then
painted with another coat of red oxide and is now ready
for flatting and undercoating. Brian Burgess put the
window glass back in and the rubber fits perfectly.
Altogether a good day. It's a pity I didn't have the DA
sander when I started it would have made all the
difference.
Speaking to Dave
Stokes the unit is to be moved across onto the No. 1
siding soon. I will need to clamp up the brake rigging
for the move. This will give better access to the No. 1
side and cab ends for when the vacuum cylinders are
replaced.
During the previous
week I had spent some time on the East Lancs. Railway at
their Diesel Gala. Earlier Brian Ashby had mentioned that
an acquaintance of his, Craig Emerson, had purchased
W55001, the Class 122 used since 1968 for route learning
duties. I had mentioned the fact that I might be
interested in buying it off him. So a visit to Longsight
was arranged where the skeletal remains of W55001 were
laying. The unit has all glass (except two sheets) intact
and two good bogies plus vacuum equipment.
After the visit it
transpired that the DMU group on the ELR had had most of
the spares. A quick call to Craig and he decided not to
continue with the purchase. So giving Railtrack a week I
put in my own bid.
It transpired that
Railtrack upon notice of non sale had put out a cutting
up order on the vehicle. My offer is the last chance to
save it for spares. Notice duly came and the cheque was
despatched so I now am the proud owner of two (10% of the
Class) 122s. W55001 is to be used as a store and for
spares.
By the weekend of July
26th and 27th the unit was still in its place in No. 2
siding. However the coach No. 9102 had been moved and the
Tkh pushed back. This allowed D5401 into the bay for
painting for Tim's daughter's wedding photos the
following weekend.
Saturday was a day of
mixed weather and between showers I managed to rub down
the remaining badly scored panels and re redoxide them.
Sunday was the first
day of using the DA sander on a virgin panel. It took
most of the morning to rub down the panel and prepare for
painting.
We decided that the
unit should be painted in green up to the guard's van
door so as to blend in with the dark green Class 27 on
the opposite road when the photographs were taken the
following weekend.
So history was made as
the panels were sanded down with the DA sander using 240
grade fine and the first coat of green undercoat applied
for over 30 years. It certainly made a difference. A top
coat will be put on next week to complete the effect. It
will also give me a good idea of any further work
required on the panels before I continue down the side.
In fact the top coat
was never applied as the undercoat was deemed adequate.
The weekend August 2nd and 3rd was spent in the
continuing saga of the bodywork. One door and one panel
was completed on the Saturday. One half of the No. 1 side
had now been rubbed and red oxided. Work has now ceased
on this side as I cannot get the scaffolding down the
side of the unit due to the overhang of the Polish Tkh
0-6-0 on the next road.
Dick has marked the
areas needed for cutting out so we can reweld patches in
during the weeks work in next week.
The Sunday was spent
on the front of the cab. One of the exhaust stacks was
removed to provide full access to the window areas. The
second will be removed next weekend. The window frames
are aluminium and look good when cleaned down to bare
metal. They will be properly prepared with the correct
etching paint before repainting.
The weeks work in was
arranged for August 11th. - 15th. to coincide with Dick
and Nick coming down from Tyseley.
The weekend before was
spent on finishing the No. 2 cab end. The other exhaust
stack was removed and areas marked out for renewal. All
bolts were drifted out and will be replaced with
stainless steel bolts and plates. The plates will be used
on the interior to protect the melamine surfaces. Both
windscreen wiper areas were badly corroded and will need
to be replaced as well as both outer tops of the window
areas. The whole area is now in red oxide.
Part
Ten
|