| Tuesday April 7th on
the railway was a lecture by Bob Bullock on the Safe
Working Of Trains. This included an old LNER film on
signalling and an overhead slide show give by Bob.
Altogether a most illuminating evening which made me
extract my old notes from the loft of my BR
correspondence course to swat up on. Another visitation
by a flooring company has been arranged for this Saturday
at 1000 hrs.. The
flooring company representative called as requested at
1000 hrs on the following Saturday April 12th. The job
presented no problems and will take two or three days.
One for latexing the floor and generally preparing it and
the second for laying the actual flooring. The colour
does not exactly match but is a dark blue with a dark
fleck pattern. I'm glad that's sorted out as it will
represent a major step forward in the restoration.
The underside of the
No. 1 body side tumblehome was then finished and red
oxided. The clips that hold the copper piping in place
were then cleaned and red oxided.
I spent the rest of a
delightful spring day in finishing the under sides of the
No. 2 tumblehome. I cut out where required and ground
down the rest ready for red oxiding. The frames on the
No. 2 side had already been re-oxided but were gone over
again and repainted together with the underside.
Sunday was once again
a fine day so I started by fashioning and welding into
place the final floor/side panel in the main saloon. I
was intending to finish off the buffer beam ready for red
oxiding but decided that some work on the No. 1 bogie
brakes was in order.
The brakes had
progressively got tighter and tighter as the unit had
been run. I originally thought that the problem was in
the linkages between brake cylinder and brake blocks
being choked with either cement dust and/or rust. After
removing and cleaning down a couple of pins I realised
the problem was not within the linkage itself but within
the vacuum cylinder. It would rise but would not fall the
full distance, being about an inch short of full travel.
This of course held the brakes on just sufficiently to
bind badly.
Once the pin between
piston rod and linkage was removed the brakes came fully
off. The piston had to be reconnected with help from a
jack and some packing to get the arm in position.
Kevin and Angie
arrived on the railway at about 1430 hrs. just in time
for dinner and a good look around. Both were duly
impressed with the railway and personnel. After Angie
rode off home Kevin, Dave Stokes and I re-addressed the
vacuum problem. With the Class 25 providing vacuum we
attempted to free the recalcitrant piston but to no
avail. It only appeared to stick slightly more. In the
end I knocked out the pin and left the brakes free. At
least the unit can be moved with no binding brake
troubles.
The general opinion
was that because the piston was rising the rolling ring
is in order and the problem is being caused by the rod
sticking. A word with Nick and Dick will be arranged for
next weekend.
Kevin in the meantime
had acquired a new 'top-hat' and seal for the piston
gland packing from Bletchley. I will fit these next
Saturday after Kevin arrives. Similarly with a quick rub
over with the Sporting Times or more exactly a fine emery
paper I will clean the piston rod of any rust or cement.
I contacted John Price
on the SVR who had had the same problem and he
recommended a complete greasing and oiling around of all
the brake rigging and a full lubricating of the whole
vacuum system with graphite. To this end I am trying to
find some graphite powder to lubricate the whole
cylinder. I shall also have a word with Chris Hatton at
Reading Depot when he returns to work on Thursday. I
shall also remove the release valve and clean that up as
it does not look in too good a condition.
During the following
week I bought 5 litres of Shipley's Chassis Black Gloss
paint ready to paint the mainframes and underside of the
bodyside tumblehomes. Providing the weather remains fine
this is one job I shall undertake over the next weekend.
Chris was at work on
Thursday when I contacted him and his immediate
pronouncement was a twisted rolling ring. He outlined a
method of getting the piston and hence ring back into
position but I suspect that doing that will only be a
temporary fix. He said do not under any circumstances put
graphite in the system. The graphite was used on old GWR
style vacuum cylinders with a fixed ring not on the later
BR equivalent with a rolling ring.
That left the decision
already made. I would not touch the assemblies now but
remove both vacuum cylinders and have them overhauled by
contract. I could then overhaul the rest of the brake
gear. How to do it was another problem. I was under the
impression that I would need to take out the bogie(s) to
effect the removal of the cylinder(s) from above so I
made enquiries to the cost of a crane hire. It worked out
at £550 per 8 hrs. The other method was to jack and
pack. Neither idea appealed so I decided to ask Nick and
Dick the Tyseley lads on Saturday. I also inquired about
the SVR overhauling the cylinders and will contact Alun
Rees next week for a quote.
On Friday the quote
from the flooring company arrived and although it was
more than I had hoped for I was quite happy to accept it.
Work on the floor will be done over the week I am working
on the roof.
Saturday, April 19th,
came and as soon as Nick and Dick were in I asked about
the cylinder removal. Word had already reached them via
Dave so Nick was ready with the answer. No need to lift
the body or remove the bogie simply drop the front
portion of the brake rigging undo the cylinder retaining
bolts and drop it down. Easy when you know how. I felt a
lot better. Tyseley has got a special hydraulic lift
device that they use when replacing vacuum cylinders.
Nick will ascertain the availability of this useful tool.
I felt even better. The job will be done over the summer
when the unit is on the back road being repainted.
Although the weekend
was fine it was cold with a north easterly wind blowing.
However onward ever onward so I started to paint the
frames and body side underpanels. It took me two days
constant work to complete both sides but they do look
good. The piping on either side can now be repainted and
refitted. I shall also purchase some signal red paint for
the buffer beams and hopefully, complete the frames for
the diesel weekend.
Kevin came down for
the Saturday afternoon and we sorted out various spares
for 55023. We did not need to undertake any further work
on the unit so we finished about 1730 hrs. I would like
Kevin to be there when we drop the cylinder(s) as we will
no doubt need the expertise for 55023 someday.
Because of the
cylinder problem I have asked that the unit only be used
with the two car set. I would like to leave the errant
cylinder disconnected as I would not like to risk a
failure in traffic. Bob has agreed to amend the plans
accordingly even if 55003 is only used as a static
exhibit.
Sunday, April 20th,
came and went as I continued painting the frames but at
the end I was in a far happier frame of mind than at the
start of the weekend. May will see the completion of a
couple of large parts of the restoration.
During the following
week I purchased paint for the buffer beams and
electrical piping i.e. signal red and orange and a light
grey for the air inlets for the heaters. I also purchased
a paint of Hammerite 'smooth' silver for the speedo and
other ancillary piping. The gods must have realised this
because from Friday until Sunday morning it rained. The
land certainly needed the rain and in the end it was a
godsend for me. When I looked in the main saloon the
floor was soaked from water leaking in during the heavy
rain.
I decided therefore to
clean the guttering and to investigate the main leak on
the unit on the No. 1 side. I found the guttering still
cluttered with years of rubbish even though the lads at
Chinnor had made a valiant attempt to clean it out. Once
clear, well as clear as I could get it, I found that the
guttering and indeed the whole body work sags in the
middle about 3/4 in. on the No. 1 side. This has been
caused by repeated removing of the guttering and
replacement of the body panels. This caused the water to
collect above the waterline of the guttering and
galvanised steel roof sheets on both sides. Hence the
rusting.
Eventually I found the
point of ingress of the water into the saloon and once
the rains had abated on Saturday afternoon I cleaned out
the hole. This of course made things worse and the bucket
used to collect the water on the inside, 2 gallons,
filled up in 25 minutes!! I stopped the hole up with wood
and material jammed into the guttering and left it until
the next fine day. The water seeped away between the
joints in the guttering and the inside remained dry. This
of course caused the problem of rust in the body panels
and window frames.
Sunday, April 27th,
dawned damp and overcast but as the day drew on the
weather brightened up. I decided that the best solution
to the leak was to grind out the rust hole and fill with
body filler. For the guttering itself I decided to put a
drain at the point the guttering went above the two small
windows between the two saloons. This being the low point
of the sag. The unit originally had been fitted with
drains on the four corner holes with pipes running down
the cab hand holds. I will refit drains at these points
but not the full length piping as this gets clogged up
too easily. The centre drain was made by using an 'L'
shaped piece of metal with a fluted brass drain inserted.
The guttering was drilled and the piece fitted to the
outside and underside of the guttering by brass bolts.
This takes the water away from the body side. Once fitted
the guttering was tested and the fitting proved a
success. The brass drain will need to be sealed better to
minimalise water leakage down the body work.
Sunday afternoon was
quite warm and the sun eventually broke through. I
painted and refitted the high side vacuum pipe along the
number one side. I also painted the wiring run along the
number two side ready for refitting. Both were done in
chassis black. I washed down the bogies on the No. 2 side
ready for topcoating also in black. Various other
ancillary bits were also cleaned down and painted black.
We finally agreed that
the unit will not be run during the diesel weekend but
will be put in the bay for static exhibition. This will
also allow me better access to the unit for the jobs
planned.
The week before the
diesel weekend, May 5th to May 9th, I decided to have a
weeks 'work-in' to get various large jobs completed. The
first was to clean and paint the roof area, the second to
get the flooring relaid and the third to clean the seat
squabs and backs. To this end I had already ordered the
roof paint from Mason's Paint of Derby, arranged with the
flooring layer to start on the Wednesday and for the
carpet cleaner to come to Cranfield also on the
Wednesday. However due to the vagaries of the English
weather this did not work out as planned.
The weekend previous,
May 3rd and 4th, was fine and warm and I began on the
arduous task of stripping down the roof. The centre of
the roof between the two sets of air ventilation inlets
was scraped down during Saturday, May 3rd. Because of
shunting movements I decided to leave the roof until
later and bolted down the No. 2 side wire run that I had
painted black the previous weekend. The unit was then
moved into the bay platform on Saturday afternoon so that
access to the roof was easier off the platform. Saturday
evening was spent in Bletchley yard assisting in the
scrapping of Class 117 No. 51359. Sunday was spent in
wire brushing the centre area to remove the cement dust
that had set on the surface from the years sojourn at
Chinnor, This was the easy part of the job.
Monday, May 5th, was a
bank holiday Monday so work was conducted around the
gathered throngs. It consisted in chipping off the old
paint from the No. 1 side and wire brushing off the
cement dust. The final job that day once the public had
departed was to clean out the guttering on the No 1 side
completely.
Tuesday, May 6th, was
a day of cold winds, rain, hail, snow and bright warm
intervals. I spent time chipping off the paint on the No.
2 side and cleaned out the saloons ready for the floorer
on Wednesday. After speaking with the carpet cleaner we
decided to give the seat cleaning a miss until better
weather was forecast.
Wednesday, May 7th,
was very much like May 6th, cold and wet. The floorer
arrived prompt at 0800 hrs. and began work. I assisted
with some small jobs he requested to make the flooring
better. However by noon it was obvious that the floor was
in a worse state than was originally envisaged. The
floorer had to use a lot more latex screed to level the
floor than was anticipated. By 1500 hrs. the floor was
screeded and was then left to dry. I continued chipping
paint off the No. 2 side of the roof.
Thursday, May 8th, was
again very much like May 7th, cold and wet. It did
brighten up in the late afternoon. The floorer arrived at
about 1300 hrs. He did what he could as the floor screed
was not dry in all areas. In fact such was the weather
that it had begun to 'sweat' in some areas, was dry in
others and had not set in others. I continued chipping
and wire brushing down the No. 2 side of the roof. I also
cleaned out the No. 2 side guttering completely.
Friday, May 9th,
dawned bright and fair and was to remain so except for a
few light spots of rain in the late afternoon. I was able
to finish off the No. 2 side cleaning down and managed to
get the first coat of etched primer on the roof. This
will protect the roof until I can do the undercoat and
topcoat(s) later in the year.
Saturday, May 10th,
was the first day of the diesel weekend and the floorer
came in at 1300 hrs to commence laying the linoleum. By
the end of the day he had floored the small saloon and
one piece in the main saloon. Everyone said it looked
good and I agreed.
Sunday, May 11th,
Angie and I arrived at about 0900 hrs. and the floorer
was already hard at work. By 1400 hrs. the floor was
complete. It definitely looked good. During the afternoon
with Dick and Brian's assistance a door window was
changed. This was the first time any of us had changed a
glass in an aluminium door.
With the remains of
the flooring Brian Ashby now has enough to replace a
piece in 9102 and Kev now has enough the patch bits in
the RBR. Brian also took the fibreglass insulation off
cuts to make seat 'ears' for 5100.
The week ended with
half the goals achieved. The flooring was a total success
and is now complete in both saloons. The roof has been
cleaned and primed and awaits undercoat and topcoat. The
guttering is clear but now requires removal in places in
order to replate the rusted side panels. The seat backs
and squabs are still in my garage uncleaned. One door
window has been replaced and the broken main window is
ready to be replaced by Dick and or Brian next weekend.
The next major task is
to refurbish the side panels. This will be started next
weekend with the removal of the guttering. I'm not
looking forward to this but Nick and Dick say it is the
only way.
As is the way with the
English weather when the following weekend arrived it was
forecast for rain. I began with grinding down the body
side panel by the guard's van. However the two car had to
painted green ready for the Thomas weekend over the next
bank holiday so I volunteered to assist before the rains
came.
Dick and Nick arrived
about 1000 hrs. and we set to replace the broken glass in
the main saloon. The removal of the glass was no problem
and the soap was soaked ready for the replacement. The
disaster struck. The piece of glass that Bletchley depot
assured me was a DMU side window glass turned out to be
1.5'' too short i.e. it didn't fit.
In order to cover up
the window I cut up a piece of white boarding and
replaced the glass with that. I shall remove all the
glass and replace with board so that all the glass can be
cleaned and the panelling can be properly sorted out.
Dick and I checked the
various stores about the line for a replacement window
but our luck was out. However Dick did find a box of air
filters so I can replace the temporary ones fitted.
We started on the two
car and finished both ends and one side of each car when
the heavens opened up and the railway was deluged.
Sunday I went down to
Chinnor to photograph 55023 for Kevin.
Monday I telephoned
City Glass who can arrange for replacement toughened
glass panes to be cut in about a week. I will have 3 main
panes and 3 small panes made. One each for Kevin, Dick
and me.
The following weekend
was late May bank holiday weekend and also the railway's
first Thomas weekend. The gods smiled and throughout the
weekend the weather was excellent.
The unit had been
moved to the back road behind the Class 45. Access to the
sides and roof is at the best poor on this road but I had
decided to make a start on re-etching the roof in
preparation for undercoating. So with the aid of a ladder
and some scaffolding the job was started.
Nick had gone for
three weeks holiday in South Africa so only Dick arrived
on the Saturday. After a brief conflab on the unit roof
we decided to remove the remainder of the glass at the
end of the day after I had finished the roof and Dick had
finished sorting out the PMV.
The roof took all most
of the day from 0900 hrs to 1630 hrs. Once finished Dick
and I removed the glass and I stored it in the main
saloon. Then with the aid of Kevin's jig-saw I cut out
the necessary hard board inserts. Dick then inserted them
in the window frames and the job was completed by 1815
hrs.
The following day,
Sunday May 25th, started warm and got warmer. I began
undercoating the unit at 0900 hrs. and finished at 1900
hrs.. When I weighed myself I had lost 8 lbs. in
weight!!! The undercoat is a deep blue colour and even if
I say so myself looks extremely good. It has covered in
one coat and the roof now awaits the top coat of matt
black. It will have to wait a few weeks as I'm fed up of
going onto the roof at present.
Richard came by and we
discussed the welding to be done on the panels. He was of
the opinion that Valentine's will not be needed and all
of what we need to do can be achieved by patching. That's
good news as he will also do the welding.
I myself was very
tired by this time so I decided to have a break on the
bank holiday Monday and help out in the signal box as I'd
put my name down for the signalman's course.
Monday once again
dawned very warm and I managed a couple of small jobs on
the unit before going into the box. One door on the unit
had been jammed ever since I had taken delivery of it. I
managed to kick it open and discovered the problem. A new
wooden pillar had been inset and the wood had warped thus
causing the door to jam. With a quick plane down the door
now opens a lot better but still needs more attention. I
also swept out the unit and laid the remaining paper to
protect the new flooring. I then retired to the box.
Saturday had seen 1500
people attend the Friends of Thomas event, Sunday 2500
people but Monday exceeded all expectations with
approximately 3000 people! The signalbox was open to
visitors. I spent a very hard working but pleasant day
being taught the ropes but then being able to explain
things to the people who came up to see the box. Finally
a whole gang of us went down in the Class 25 to move the
bufferstops across so that 'Thomas' could leave for the
SVR on the following Wednesday.
Angie's dad and step
mother were visiting Bedford on a short break so all four
of us came to the railway for a short visit on the
Tuesday. This was the first time that John and Gay had
seen the unit. What they made of it I'm not sure. I think
it was a lot bigger than what they expected. Both engines
fired up on cue and everyone was pleased, me especially.
I think the unit feels at home I know I do.
Part
Nine
|