| Sunday was spent, at
home, cleaning and refurbishing the heater vents ready
for replacement when the saloons are refloored and
finishing the final door inserts. A supplier of glass fibre
insulation slabs has been found and over the next few
weeks I will be reinstating the insulation into the
panels that are in order ready for refitting of the new
internal panelling itself.
The following Friday,
January 10th, I bought a pack of the slab insulation and
ordered the new beading for the side panel fitting. This
beading is cut so that the internal melamine side panels
sit on the beading about 0.5" off the flooring. The
beading is then screwed onto the metal panels that form
the join between floor and metal side panel. This fixing
holds the melamine panels in place.
On Saturday, January
11th, began the replacement of the insulation in the
small saloon. The initial task was to finish off grinding
down and removing any other rust patches on the internal
body panels and coating with red oxide. Next the new
window drain tubes were threaded through the holes in the
cover panels. By mid afternoon the small saloon was
completely reinsulated and ready for the final welding
and replacement of the internal melamine panels.
The metal strip that
the seats are screwed to and that had been removed to
allow renewal of the rotten floor boarding was
refurbished and refixed to the floor. All the floor seat
fixing strips will need to be cleaned down and red oxided
then accurately measured. This is required as they will
be covered by the flooring when replaced and the fixing
points for the seat bolts/screws need to be known for
easy refixing.
About 11 o'clock Andy
Fowler arrived and assisted by making a good start on
removing the flooring from the large saloon. By the mid
afternoon 75% of the large saloon was completed.
Following on Sunday the flooring in both saloons was
removed by Andy. The whole unit was devoid of flooring by
lunch time. One curious find was a hole about 4" x
3" in the floor above the No. 1 gearbox. As I could
think of no reason for it's existence I plated it with
3/8" plywood.
The unit was cleared
out and is now ready for the final grinding out of any
rust patches so that the new drain tubing can be inserted
and the insulation cut and fitted to the side panels. The
final job undertaken was to change the oil in the
generator.
It transpires that the
hole was cut out to facilitate the fitting of a hot water
type heater similar to that found in the cabs. Evidently
it was not a success.
The next Saturday,
January 18th, the body side panels in the main saloon
were ground down and painted with Dinitrol. The only
panels that were not touched were the two panels directly
behind the No. 1 cab. These panels were fitted with
insulation ready for interior panelling. One base frame
in one of the windows was found to be extensively
corroded so it was removed and ground down ready for
Dinitrol and red oxide. The door footplates were lifted
and the wooden areas painted with a proprietary wood
preservative for rotten and slightly damaged wood. The
infusion had to be left for a week to ensure it had dried
properly. The solution soaks into the wood and dries as a
resin thus ensuring the longevity of the remaining good
wood. The penultimate floor/side panel was redoxided and
is now drilled and ready for fitting as soon as the
welding is complete on the interior framework.
Sunday I spent the day
at home working on the interior window frames and
fabricating a new base frame for the removed one. Andy
worked on the unit during the Sunday and finished off the
red oxiding of the remaining interior metal panels ready
for the fitting of the insulation during the next
weekend.
During the week the
first of the interior window frames was finished. All
that is still outstanding on this frame is the fitting of
corner pieces and putting in place. The woodstain colour
chosen was teak. Saturday, January 25th, saw the fitting
of new window drain pipes in the remaining windows of the
main saloon, the new window base frame, the fitting of
the remaining insulation in the main saloon by Andy and
the filling with 'plastic wood' in the door wells ready
for refitting of the foot plates. The two cabs were also
made ready by myself by red oxiding the exposed metal
panels above the driver's desk and the subsequent fitting
of the insulation in the recesses.
Kevin arrived in the
early afternoon to discuss the situation of the running
agreement and the 'board's' decision to ask me to remove
the unit by the end of February. It appears that not all
the board knew what was going on and that the decision
had upset a lot of people. The board meeting to discuss
the situation is on Wednesday, January 29th. As I have
already asked three railways, the NVR, SVR and
Shackerstone, for permission to move the situation is
quite delicate and at present I am disposed to move. Just
in case the unit is to move the springs and other
requisite points were oiled and made ready. The interior
of both saloons is now more or less ready for reflooring
and once the internal welding is complete ready for the
new internal panels. The two cabs are now ready for
internal panelling to be replaced. A start can now be
made on the exterior of the unit with especial attention
being given in the short term to the guttering, the roof
and the plating between the tumblehome plating and the
mainframes. Once these are in order the major task of the
main body work can start.
Sunday, January 26th,
was spent once again at home fabricating the final
floor/side panel out of a piece of thin gauge sheet
metal. All that is required is that it is drilled, red
oxided and screwed in place. Later the beading that
attaches the internal formica side panels to the
floor/side panel metal pieces was painted with wood
preservative and late on Sunday given its first coat of
teak stain. At lunchtime Kevin and I had a trip out to
look at 55023 which is now on the scrap line at BY depot.
Similarly the last remaining Class 116 driving car was on
the depot and in good overall condition but with thrown
exhauster/alternator belts.
During the following
week more pieces from the internal window frames were
cleaned down, stained and varnished. A start was also
made on replacing the broken ends of the corner pieces of
the frames. The pieces will need filling and rubbing down
before staining and varnishing but the new corners should
last for some considerable time. I have also had 10 new
corners fabricated in Mahogany by Bletchley Timber using
one of the old corners as a template. The finish is
excellent and the fitting is also very good. I will have
4 or 5 spare corners at the end of the rebuilding. The
beading for the internal panels was restained and
varnished and is now ready for putting in place once the
vinyl floor covering has been relaid.
The following
Saturday, February 1st, the batteries were put on charge
utilising the new battery charger. The most that appeared
to go into the batteries using my generator was 3 or 4
amps on 12 volts and is not satisfactory. I will split
the batteries into two banks and retry. The engines were
tried at the end of the day with a singular lack of
success although the battery condition indicator
indicated good batteries but not fully charged ones. The
starter motor(s) did not even engage.
The door footplate
fittings were refitted into the refurbished foot wells.
They have all taken properly and are now fitted securely.
The last floor/side panel was red oxided and fitted. The
final trimming of the flooring around the sliding door
fittings was finished and the saloons were swept out
ready for reflooring.
At last two
outstanding jobs from the end of last year were tackled.
The two belts on the No. 1 engine, No. 900, to the right
angled drive were changed and the gearbox final drive end
bearing seal, also at No. 1 end, was dismantled ready for
replacement. The seal, seal housing and bolts were taken
home for cleaning and replacement. The seal has to be
driven out of the housing and the new one driven in.
After much head scratching I completed the task by using
the old seal to drive home the new seal to its full
extent. Easy when you know how. The manual was followed
explicitly and the seal was packed with the correct
grease. When dismantled there was no grease on the seal
edges at all. I had also been given a set of rubber 'O'
rings by John Price on the SVR for what I did not know
but I was to find out.
The gearbox final
drive and seal is held in place by a huge castelated nut,
washer, 'O' ring and split pin. The 'O' ring on the
gearbox output shaft when dismantled was flattened and
dry. The washer used with the castelated nut is backed by
a rubber seal and with the 'O' ring seals the drive
flange end to the gearbox output shaft. In undoing the
nut very little effort was expended so I suspect that the
main seal was in fact in good order but the 'O' ring was
failing and the nut was undertight. I sealed the washer
with Loctite and tightened the nut up an extra notch. All
the nuts on the connecting bolts to the final drive were
replaced with new Nyloc nuts. The gearbox turned with no
undue noises or effort and a litre of gearbox oil was put
in. Another litre of oil will be required and the gearbox
tested.
The week was spent on
the continuing refurbishment of the remaining broken
window frames
Saturday, February
8th, was spent at work and as Sunday dawned wet and windy
Chinnor was given a miss and more work was done at home
on the window frames.
The week was spent on
refurbishing the remainder of the broken window frames
and I will soon be in a position to be able to make up
these frames. This leaves just the 'good' frames to be
refurbished and the broken frames to be rebuilt.
During the week I took
delivery of a new battery charger from Deakin Davensets
of Rugby and Saturday February 14th was the first day of
trying it out. After arrival at Chinnor I tried to start
the engines but apart from a 'click' as the stop solenoid
came out no movement was discerned from the starter motor
on either side. I wired the charger into the BR charger
socket but the use of crocodile clips from the charger
leads gave problems so this idea was abandoned.
Wiring the charger
across one bank of batteries terminals but charging each
bank in parallel i.e. two sets of 12v batteries as
opposed to one set of 24v, gave an input current of
approximately 3 amps. I was most disappointed as I
expected a far higher charging rate. I left the charger
going for most of the day but did not try to start the
engines again.
Of the three railways
that had been contacted regarding a future home for the
unit only the Severn Valley railway had responded albeit
in the negative. I decided therefore to approach a
railway more or less on my doorstep, the Northampton and
Lamport Railway. I spoke to Mark Herbert who gave me the
telephone numbers of the railway and of the Chairman, Bob
Faulkner.
I telephoned the
railway and as luck would have it they were talking about
future developments on the railway one of which was an
extra DMU to supplement the Class 108/117 hybrid unit
already on the line. The Class 108 is a driving trailer
and the Class 117 is a power car. Therefore if the Class
117 fails the whole unit is a failure. With 55003 the
railway will have the possibility of running a 1, 2 or 3
car set. with the bubble covering for a failure in the
117 and vice versa. A meeting was arranged for the
following Sunday February 15th. The meeting went well and
a verbal agreement was arranged subject to board approval
etc.. The board meeting was arranged for Wednesday
February 26th and a visit to inspect the unit for
Saturday March 8th.
I spent the next two
weekends on holiday in Germany photographing eastern
German narrow gauge.
Upon return on Sunday
March 2nd Bob had called to ensure the visit was on. So
on the following Saturday I arrived at Chinnor at 0830
and began recharging the batteries. I split the banks
into two and charged each set up separately. On one bank
all batteries were at 2.1 v each but on the other bank
two batteries were down at 1.9 v. I think this is the
problem of the starting. I polished both cab desks and
made sure 55003 was in as good a condition as possible.
However the inspection went well and formal agreement was
reached for 55003 to go to Pitsford.
I oiled all round to
make sure the unit was ready for movement and decided to
retry the engines at about 1530 hrs.. The batteries were
reconnected and as if in anticipation of the move the
engines fired up ON THE FIRST TURN and I was happy. I
checked the No 1 gearbox seal and the box was dry. I
started work on the frames and chipped off the old paint
from the No. 1 cab end buffer beam and painted it in red
oxide then retired to the pub for a welcome beer.
The move was agreed
with Bob and Allelys' for delivery to Northampton on
Thursday 27th March. The move is to be a double move as
Kevin has been successful in purchasing Class 121 55023
from Bletchley depot. This will be a good acquisition for
Chinnor as it is in a more or less complete condition.
Although some work will need to be done on making 55023
water tight and replacing interior panelling and it comes
with no spares.
The last of the 5
dismantled interior window frames was glued together
during the week and a start was made on the 'good'
complete frames. I expect to be able to complete one a
week during the spring and summer.
The following Saturday
was spent at work however I ordered a MIG welder from a
firm in Nottingham. This will allow me to get on with
welding the unit in my own good time. I managed to get to
Pitsford Station during the Sunday. I had gone ostensibly
to explain the moving situation to Bob and Dave and after
a walk up and down the line assisted Dave and Martin in
cleaning down the traction motor blower assembly off
26010.
The week following was
spent in cleaning down the six small window frames and
gluing new corners on where required. The final weekend
at Chinnor was Saturday and Sunday March 22nd and 23rd.
On the Saturday I succeeded in removing the top steps
from the No. 1 side despite being hemmed in by the
recently arrived Class 25 D7529. The engines ran up with
no problems and after leaving for a while to warm up were
run hard to clear the exhaust passages. This was achieved
well within 30 minutes when the exhaust ran clean.
In the No. 1 cab I
noticed that below the indicator box the melamine
panelling had been forced out of its position and when
pressed showered rust. I removed the panelling and found
the reason to be water leakage from the glass front down
and under the route indicator box. This had caused the
wooden base piece of the box to rot and the main cross
member to rust. The metal pieces in the indictor box were
duly cleaned out, coated with Dinitrol RC800 and when dry
red oxided similarly the main cross member. Whilst Kevin
was on a 'steam fireman's' course I took time to solder
the contact light in the No. 1 cab into place only to
find the bulb had gone. Finally in the cab I measured up
the side panelling ready for purchasing and fitting.
Whilst running the
engines up I noticed that the air pressure had risen to
well over 100 lb./sq.in. and had not been 'unloaded' by
the unloader valve. I released the air by opening one of
the air valves on the No. 2 side until Kevin and I could
take a closer look at the unloader valve itself. I oiled
round to make sure everything was in order for the shunt
and move.
Kevin came down
shortly after noon and we ran the unit up. Once
sufficient air pressure had built up Kevin blew down the
air tank on the unloader or No. 1 side. A fair amount of
water came out. Once cleared the system was allowed to
blow through to clear the pipes and tanks of any further
water. The unloader was tried again but failed to work.
After consultation with Dave Potter we slackened off the
adjuster on the unloader and tried again. The unloader
began to work albeit somewhat slowly and now does not
allow the air pressure to exceed 90 lb./sq.in..
Finally the unit was
shunted into position ready for removal by Allely's on
the following Wednesday evening.
This meant that no
further work had to be done on the unit at Chinnor and so
Sunday was spent at home finishing the small window
frames. The corners were already in place a so with a bit
of plastic wood and sandpaper were rubbed down to the
correct profile. Three coats of stain were applied and by
1900 hrs. all six frames were ready for varnishing. In
between coats I managed to rub down two of the remaining
five large window frames ready for fitting with new
corner pieces and staining.
I was at work on the
following Wednesday, March 26th when Kevin phoned with
the news that the rig that was to transport the units had
failed with a split oil pipe on the return journey from
the Mid Hants. The rig was returning to Warwickshire for
repair and the operation was to be put back 24 hours.
I still took the
Thursday off and arrived at Bletchley depot at 1130 hrs.
to the sight of no one. I waited until 1200 hrs. when
Kevin arrived. He telephoned Allely's who informed us
that the transporter was well on its way and would arrive
within the hour. It arrived at 1230 hrs. 55023 was loaded
up by 1530 hrs. and both rig and assembled volunteers set
off for Chinnor.
We arrived at Chinnor
just as the rain clouds were gathering at about 1700 hrs.
The rig arrived at 1930 hrs. having suffered various
adventures on the way. 55023 was unloaded by 2100 hrs.
and 55003 was loaded by 2200 hrs. The crew then left for
home as another crew were booked to move 55003 the
following morning. The trailer was then parked up and I
left for home arriving at 2330 hrs.
Good Friday dawned
fair and I was at Pitsford for 0930 hrs.. Bob had already
contacted the crew who were already on the way to
Chinnor. Kevin called home and Angie called the railway
to say that the unit had left for Northampton at 1010
hrs. Later that morning the local bobby called in for a
'social call' and we mentioned the pending arrival. The
Northamptonshire Police Traffic Division had not
delegated anyone to meet the transporter so our local
bobby did the job himself meeting the rig in the A14.
We had just brewed up
when a call came in that the whole ensemble was only 10
minutes away from Boughton Crossing. We all jumped into
the train and set off hot foot, or hot wheeled, for the
end of the line. Andy Entwhistle and his gang had already
removed the fence, slewed the buffer stops and laid the
connecting rail. He set off in the dumper truck with the
keys to open the gate at Boughton Crossing. As we arrived
at the crossing we saw the first police car arrive and
stop on the Northampton side of the crossing whilst our
local bobby who had followed the load stopped on the
Chapel Brampton side of the crossing.
The rig was positioned
so that any residual build up of traffic could clear. It
was then allowed to negotiate a three point turn and
proceed up the walk way to the railhead. Without many
problems 55003 was unloaded and hauled onto NLR metals
gathering a fair number of interested persons on the way.
The rig was duly reassembled and sent on its way and the
unit was towed into Pitsford Station by D5401 &
25035.
55003 was positioned
at the south end of the run-around loop and I prepared
her for a start up the following day.
Easter Saturday, March
29th, was a glorious day and I began to strip down the
No. 1 side frames ready for painting. I ran the unit up
and tested the unloader valve to make sure it was
functioning properly, it was. It was decided that we
would move 55003 and position it as follows, the Class
117 at the south end, the Class 108 trailer in the centre
and the Class 122 at the north end. 55003 fired up with
no problems and was soon running with a clear exhaust.
Dave Stokes then came down and after I had reengaged the
final drive the engines were restarted, the brakes
released and the unit was moved for the first time on the
NLR. It was duly coupled up to the two car set and all
three cars were repositioned in the loop. So ended my
first day on the NLR.
Easter Sunday was
spent continuing with the preparation of the frames when
Bob and Dave came to say the first official run was to be
that afternoon after the 1400 hrs. steam train departure.
Because the whole line is fully signalled there are no
problems running more than one train at a time. The units
were run up and sat at the inner home signal awaiting the
departure of the service train. At precisely 1403 hrs.
the Peckett took the service train out of Pitsford
southbound. The DMU followed as soon as the road was
clear and ran into the Ironstone Sidings with no problems
except for a slightly dragging brake on 55003s No. 2
bogie. Later that afternoon the exercise was repeated in
reverse with the three cars running non stop through
Pitsford for the north. A goodly amount of people saw the
first official run in glorious weather.
After another couple
of hours work I left for home tired but very happy. Bob
was so pleased that he was planning to run the unit(s) in
the same way the following day for the gathered crowds.
The railway had played host to over 1300 people on the
first two days of Easter. Everyone was happy.
I spent Easter Monday
in finishing off the small window frames and preparing
the final five large frames for staining and varnishing.
I also tested my new MIG welder. The railway on the
Easter Monday played host to 995 people making a grand
total of over 2200 people to have visited the line during
the holiday period.
The paint duly arrived
from Masons on Thursday April 3rd ready for my weeks work
in during the first week in May. I also purchased some
'liquid rubber' compound for the guttering. This will be
utilised as the roof is repainted and should eradicate
all leaks into the main body of the unit. The final five
large window frames were finished on Friday April 4th, at
last, and now all complete windows are stored in the
garage ready for refitting.
I spent the next
weekend April 5th and 6th at Pitsford. On first arrival I
noticed something strange about the driving cabs. I could
see through the windows! Bob had spent a couple of hours
on the Easter Monday cleaning off the cement dust with
Brasso and Scotchbrite pads! Compared to earlier in the
week the windows were now in pristine condition. They
will need finishing off properly but show what a mess the
whole of the unit had become whilst at Chinnor. I'm
extremely glad I moved. In between calls from work I
managed to finish cleaning down the frame on No. 1 side
including removal of the piping down this side. The bolts
will need to be replaced as all are wasted and some
snapped on removal. I would have red oxided the frame but
I forgot to bring my angle grinder so this had to wait
until the Sunday. The man from GRA flooring did not turn
up so the flooring is still to be sorted out.
Because I had
forgotten my angle grinder I could not do any welding
until Sunday. I began by making up two 'L' section cross
pieces to finish off the frame and after seeking
assistance from Richard Boardman I welded them into place
as I had managed to get the welder to fail. It would not
drive the core wire through to the welding tip. Evidently
this is a problem with a gasless MIG welder. Still you
live and learn. I then fabricated and welded into place
the bottom half of the door upright in the small saloon.
This allowed me to fix the floor/side member so that the
flooring can now be completed in the small saloon as and
when we require. I was very pleased with the result as my
welding got better the more practice I had.
The rest of the
afternoon was spent grinding down and then red oxiding
the No. 1 frame ready for painting. This leaves the
underside of the tumblehome to be cleaned and red oxided
and the bogie frames on No. 1 side. On the No. 2 side the
underside of the body panelling need looking at and them
a complete clean down ready for re-red oxiding. I can
then paint the frames and bogies in the customary gloss
black.
Part
Eight
|